Toll Road Construction Has Started
Kaltim people's desire to have the toll road will soon materialize. East Kalimantan Governor Faroek Ishak Awang initiate the start of construction of the inauguration of the freeway between the Balikpapan-Samarinda. Inauguration done in Batakan, Aberdeen, on Wednesday (12/01).
Awang said the motorway was first built in Kalimantan and includes tons of the national road network. This of course requires the support of all parties to menyukseskannya as evidence of the seriousness of the region to build infrastructure.
"The highway is part of the General Plan of the National Road Network. This is determined by Ministerial Decree (Decree) No. 567/KPTS/M/2010 Public Works. I ask that all parties come together to achieve successful development of toll road to run smooth, "said Awang.
On that occasion, the governor said the road toll is much needed community. Moreover, the number of vehicles Samarinda-Balikpapan more years the number would increase. To that end, the infrastructure especially the road was felt necessary.
"Later, the provincial government will also build a toll road until Maloy - East Kutai. Consequently, this development will be felt for 2.3 million people from 3.5 million population of East Kalimantan, "he added.
Awang also said it had invited a number of domestic and foreign investors to participate. He assured the tempo is not too long, the road is definitely crowded as economic and population growth in East Kalimantan is so fast.
"I've invited a few investors to build this road. Two investors are ready to invest in this toll. But they do not want published, "said the Governor.
According to the study, the project is estimated to require funding Rp.6, 2 trillion. That figure consists of Rp 5, 03 for construction and Rp1 trillion, 23 trillion land acquisition. Of these, Rp.2 trillion budget sourced from East Kalimantan issued a multi-year system (multiyears) starting 2010-2013. The remaining funding is allocated from foreign soft loans (loans) to Rp. 3 trillion and investors about Rp1, 2 trillion. (Gus)
Wednesday, September 7, 2011
Kaltim Allocate Rp 2 T Fishing Toll Road Investors
SAMARINDA - East Kalimantan provincial government began construction of the freeway Balikpapan - Samarinda to set aside Rp 2 trillion as initial capital. Kaltim budget funds allocated through the multi-year is called the Head of Technical Planning Section of Road and Bridge Department of Public Works Highways Sector East Kalimantan, H Joko Setiono, in order to lure investors to want to build the freeway (freeway) or called a toll road is crowded.
"Investments in start-up capital is just as inducement to investors to be willing and interested in realizing the construction of toll roads. Later, when it's investors who build, then the provincial government investments in shares will be taken into account," Joko said when answering a question a number of communities in East Kalimantan interactive dialogue titled 'Development Toll Road East Kalimantan 'on ABC News Radio FM, Samarinda, recently.
Freeway construction that has been launched Governor Faroek Ishak Awang, last January, as is known still reap the pros and cons. Most people do not agree with this freeway project, except for better provincial mempriotaskan repair roads that exist. But, most of the others actually support the bold move of Governor Faroek to realize toll road only in Borneo.
What if there was no investor? "Otherwise there are also investors who want to build a freeway along the 99.2 miles, then Rp 2 T is missing. But the project itself must still we go on. And I'm sure when the prospects for economic growth in East Kalimantan is growing, especially in two major cities - Balikpapan and Samarinda - then the investor would have, "explained Ricardo, one of three sources other than the Chairman of Commission III DPRD Kaltim, H Syahrun HS and Head of Documentation and Information (Dokinfo) Diskominfo Kaltim, Nurdin AR.
He calls, the initial concept of this freeway actually started in 2002. During Governor Suwarna AF who want to realize the highway road Balikpapan - Samarinda. Being the Department of Public Works (now Ministry of Public Works) less agree with the concept of highway, except with the concept of a primary artery. Then in 2005, the concept of highway construction Samarinda - Balikpapan it stagnates.
Well, Joko explained, in 2009 Governor Faroek re-rolling the program. The feasibility study was carried out, including conducting further studies on the growth of economic development of East Kalimantan next few years. The results of the financial assessment or FIRR (Financial Internal Rate of Return) as a requirement of building a toll must be above a minimum of 12%, East Kalimantan is considered not feasible to build toll. FIRR value of his study is still at 7.74% rate.
However, studies of economic development or growth EIRR (Economic Internal Rate of Return) is quite encouraging. "Kaltim EIRR reaches or exceeds 20.14% FIRR 12% minimum requirement. What does that mean? Economically Kaltim feasible to build a highway, even though financially (FIRR) is not feasible. It is therefore necessary attention and support of central government funds in order to realize This freeway road projects, "said Joko representing the Head of Department of Public Works this Kaltim.
East Kalimantan highway project is also, according to Ricardo, was approved by the Ministry of Public Works. Was decanted through a decree of the Minister of Public Works No. 567 dated November 10, 2010, which include toll roads Samarinda - Balikpapan as part of national road network development highway. In fact, BPJT (Toll Road Regulatory Agency) of the Ministry of Public Works again soon conduct a feasibility study to embrace investors who want to build a road freeway that's scheduled for completion in 2013.
"I think, no more doubt. The road we have to wake up this freeway. The question now is how we are both struggling to get government funding in order to realize the toll this project," said H Alung - friendly greeting chairman of Commission III DPRD Kaltim - adding that, if Kaltim Jol did not build roads from now, when will society Kaltim yes this could have toll roads like in Java and other areas.
Related to the allocation of budget funds worth Rp 2 T is called Joko as inducement to the investor funds to realize the freeway. Budget allocation was used to build the road and land acquisition, community land. Moderate community itself is expected to Joko not worry, because the term compensation has now been changed to replace a profit in any land acquisition affected by road construction. (Dil / diskominfo)
"Investments in start-up capital is just as inducement to investors to be willing and interested in realizing the construction of toll roads. Later, when it's investors who build, then the provincial government investments in shares will be taken into account," Joko said when answering a question a number of communities in East Kalimantan interactive dialogue titled 'Development Toll Road East Kalimantan 'on ABC News Radio FM, Samarinda, recently.
Freeway construction that has been launched Governor Faroek Ishak Awang, last January, as is known still reap the pros and cons. Most people do not agree with this freeway project, except for better provincial mempriotaskan repair roads that exist. But, most of the others actually support the bold move of Governor Faroek to realize toll road only in Borneo.
What if there was no investor? "Otherwise there are also investors who want to build a freeway along the 99.2 miles, then Rp 2 T is missing. But the project itself must still we go on. And I'm sure when the prospects for economic growth in East Kalimantan is growing, especially in two major cities - Balikpapan and Samarinda - then the investor would have, "explained Ricardo, one of three sources other than the Chairman of Commission III DPRD Kaltim, H Syahrun HS and Head of Documentation and Information (Dokinfo) Diskominfo Kaltim, Nurdin AR.
He calls, the initial concept of this freeway actually started in 2002. During Governor Suwarna AF who want to realize the highway road Balikpapan - Samarinda. Being the Department of Public Works (now Ministry of Public Works) less agree with the concept of highway, except with the concept of a primary artery. Then in 2005, the concept of highway construction Samarinda - Balikpapan it stagnates.
Well, Joko explained, in 2009 Governor Faroek re-rolling the program. The feasibility study was carried out, including conducting further studies on the growth of economic development of East Kalimantan next few years. The results of the financial assessment or FIRR (Financial Internal Rate of Return) as a requirement of building a toll must be above a minimum of 12%, East Kalimantan is considered not feasible to build toll. FIRR value of his study is still at 7.74% rate.
However, studies of economic development or growth EIRR (Economic Internal Rate of Return) is quite encouraging. "Kaltim EIRR reaches or exceeds 20.14% FIRR 12% minimum requirement. What does that mean? Economically Kaltim feasible to build a highway, even though financially (FIRR) is not feasible. It is therefore necessary attention and support of central government funds in order to realize This freeway road projects, "said Joko representing the Head of Department of Public Works this Kaltim.
East Kalimantan highway project is also, according to Ricardo, was approved by the Ministry of Public Works. Was decanted through a decree of the Minister of Public Works No. 567 dated November 10, 2010, which include toll roads Samarinda - Balikpapan as part of national road network development highway. In fact, BPJT (Toll Road Regulatory Agency) of the Ministry of Public Works again soon conduct a feasibility study to embrace investors who want to build a road freeway that's scheduled for completion in 2013.
"I think, no more doubt. The road we have to wake up this freeway. The question now is how we are both struggling to get government funding in order to realize the toll this project," said H Alung - friendly greeting chairman of Commission III DPRD Kaltim - adding that, if Kaltim Jol did not build roads from now, when will society Kaltim yes this could have toll roads like in Java and other areas.
Related to the allocation of budget funds worth Rp 2 T is called Joko as inducement to the investor funds to realize the freeway. Budget allocation was used to build the road and land acquisition, community land. Moderate community itself is expected to Joko not worry, because the term compensation has now been changed to replace a profit in any land acquisition affected by road construction. (Dil / diskominfo)
Sunday, February 27, 2011
Without the Minister of Public Works, Freeway Kaltim Started
Without the presence of Minister of Public Works Djoko Kirmanto Ir, construction of the freeway (freeway) or a toll road in East Kalimantan worth trillions of rupiah remained began, marked by the installation of the main pile on the side of Ring Road III Manggar, Balikpapan East (12/1/2010) .
East Kalimantan Governor Awang Faroek Ishakdidampingi several regional head officials (Mayor / Regent), whose land this project passed, seemed cheerful when pressing the siren as a signal the start of construction of the highway that connects the Balikpapan-Samarinda-Bontang to Sangatta.
"I've long counted the toll road in East Kalimantan is 241 kilometers from the street Rua Penajam-Balikpapan-Samarinda-Bontang-Sangatta-Malaoy, and Samarinda-Tenggarong. Meanwhile, residents who resided in the vicinity there are 2.3 million people. So this project really touches people, and not lighthouse project, "said Awang Faroek Governor at the dedication.
Awang asks all parties involved to support the implementation of the construction of the freeway in East Kalimantan that also say the national motorway network. In particular, the governor asked the Mayor Imdaad Hamid Balikpapan, Samarinda Mayor Mayor H Syaharie Jaang, Regent of Kutai Karta Rita Widyasari State, East Kutai Regent Irsan Noor for guarding each toll road project through their respective regions.
At this time the construction of the highway began in the Balikpapan-Samarinda road along the 99.02 miles. Construction of road pavement using the system rigid pavement (concrete) with a width of 36.9 meters of the road is divided into 2 lanes to 6 lanes, and each lajurnya width of 3.6 meters. Costs range from 6.2 trillion consisted of Rp 5 trillion for the construction and Rp1, 2 trillion of land acquisition.
"The length of the road and the cost of registration is not nothing compared to the construction of toll roads in Java," added the governor.
In addition to major highway projects, it is also built Aberdeen Road along Ring Road III 11.12 miles as road access to the Balikpapan-Samarinda highway from Aberdeen Regional Airport Sepinggan and East. The plan consists road from 2 lanes to 6 lanes, each lane width of 3.6 meters. The cost spent to reach 778.4 billion for construction, while land acquisition is borne by the City Government of Balikpapan.
Previously, in the past year has nevertheless built a starting point Balikpapan-Samarinda highway, located 400 meters east of Balikpapan KM 13 North. Road access is part of the road plan Ring Road III Balikpapan is only 400 meters long, was built as much as 2 lanes to 4 lanes. Construction costs reached 11.5 billion for land acquisition, and construction cost of Rp90 billion .***
Profile of Toll Road Balikpapan - Samarinda
Development of road infrastructure is an absolute necessity for the development of transportation, economic improvement and regional development in East Kalimantan Province. In efforts to comply with the road infrastructure, and taking into account the limitations of the East Kalimantan provincial government funds on one side and sees private investment opportunities on the other hand, the East Kalimantan provincial government make policies to attract private investment in the highway / freeway / Toll By involving the private sector is expected to accelerate infrastructure provision for the increase in social welfare can be achieved. East Kalimantan provincial government plan Free Road Construction Barriers / Freeway / Toll Road along 241 kilometers of road covering Penajam - Balikpapan - Samarinda - Bontang - Sangata - Maloy / Samarinda - Tenggarong.
In the Government Regulation No. 26 of 2008 regarding the National Spatial Plan (RTRW-N) have been set free Road Network System Barriers / Freeway / Toll in East Kalimantan Province is road:
a. penajam - Balikpapan
b Balikpapan - Samarinda
c. Samarinda - Tenggarong
Based on the Decree of the Minister of Public Works No.. : 567/KPTS/M/2010 About the General Plan of the National Road Network. On 10 November 2010, the streets of Balikpapan - Samarinda designated as National Road Toll Roads In accordance with the above, the East Kalimantan provincial government has started the Free Road Construction Barriers / Freeway / Toll roads along the Balikpapan-Samarinda 99.02 Kilometers.
Source: http://www.kaltimprov.go.id/kaltim.php?page=detailberita&id=4512